2026 Distribution Main Improvements- Glen Avenue Water Main Replacement Project
Ridgewood Water will be upgrading critical water main infrastructure along Glen Avenue (Bergen County Route 82) in Midland Park and Ridgewood. This work is supplementary to the West Glen Booster Pump Station recently installed at the intersection of E. Glen Avenue and Oak Street. After completion, the newly upsized water main will further assist in improving water pressure and reliability in a low-pressure area (located at the top of the hill).
- Awarded Contractor: Montana Construction, Inc.
- Total Project Cost: $4,723,000.00
- Location: Glen Avenue from Highwood Ave (Midland Park) to Oak St (Ridgewood)
- Approximate Length of Main to be Installed: 7,500 linear feet
- Anticipated Start Date: Early to Mid September 2026
- Estimated Duration: 4-6 months
- Final Paving Restoration: Spring/Summer 2027