PFAS RESOURCES

Take a Look at our PFAS Treatment Facilities

Carr Treatment Facility 

Project Status: Construction Completed; Facility in Operation

Completed: September 2019

Twinney Treatment Facility

Project Status: Construction Completed; Facility in Operation

Completed:  August 2022

Ravine Treatment Facility

Project Status: Under Construction; Began in April 2023

Expected Date of Completion: April 2025

Prospect Treatment Facility 

Project Status: Under Construction; Began in August 2023

Expected Date of Completion: August 2025

Ames Treatment Facility

Project Status: Under Construction; Began in April 2024

Expected Date of Completion: April 2026

East Ridgewood Treatment Facility

Project Status: Under Construction; Began in August 2024.

Expected Date of Completion: December 2025

West End Treatment Facility

Project Status: Under Construction; Began in August 2024

Expected Date of Completion: December 2025

Wortendyke Treatment Facility

Project Status: Under Construction; Began in October 2024

Expected Date of Completion: December 2026

Cedar Hill Treatment Facility

Project Status: Under final design and permitting; Pending cultural resource approval, construction will begin in Spring 2025

Expected Date of Completion: December 2026*

Eastside Treatment Facility

Project Status: Under final design and permitting; Construction planned to begin Spring of 2025

Expected Date of Completion: October 2026*

 

Main Treatment Facility

Project Status: Under final design and permitting; Construction planned to begin Spring 2025

Expected Date of Completion: October 2026*

Mountain Treatment Facility

Project Status: Under final design and permitting

Expected Date of Completion: October 2026*

*Pending Award Date