PFAS RESOURCES
Wortendyke Treatment Tank Installation
Ridgewood Water has contracted, Sovereign Consulting to construct the PFAS Treatment Facility located in Midland Park. This is part of Ridgewood Water's commitment to investing into the future sustainability of the Ridgewood Water water system and executing the PFAS Treatment Master Plan. This treatment facility will be treating 9 wells in the system.
For more information on individual facilities, please see below.
Take a Look at our PFAS Treatment Facilities
Carr Treatment Facility
Project Status: Construction Completed; Facility in Operation
Completed: September 2019
Twinney Treatment Facility
Project Status: Construction Completed; Facility in Operation
Completed: August 2022
Ravine Treatment Facility
Project Status: Under Construction; Began in April 2023
Expected Date of Completion: November 2025
Prospect Treatment Facility
Project Status: Under Construction; Began in August 2023
Expected Date of Completion: October 2025
East Ridgewood Treatment Facility
Project Status: Under Construction; Began in August 2024.
Expected Date of Completion: January 2026
West End Treatment Facility
Project Status: Under Construction; Began in August 2024
Expected Date of Completion: January 2026
Ames Treatment Facility
Project Status: Under Construction; Began in April 2024
Expected Date of Completion: April 2026
Wortendyke Treatment Facility
Project Status: Under Construction; Began in October 2024
Expected Date of Completion: February 2026
Cedar Hill Treatment Facility
Project Status: Under final design and permitting; Pending cultural resource approval, construction will begin in Fall 2025; Bid Opening Scheduled for October 9th 2025
Expected Date of Completion: December 2026*
Eastside Treatment Facility
Project Status: Anticipated start date September 2025
Expected Date of Completion: October 2026*
Main Treatment Facility
Project Status: Under final design and permitting; Construction planned to begin Fall 2025
Expected Date of Completion: October 2026*
Mountain Treatment Facility
Project Status: Anticipated start date of September 2025
Expected Date of Completion: October 2026*
*Pending Award Date