PFAS RESOURCES

Wortendyke Treatment Tank Installation

 

 

 Ridgewood Water has contracted, Sovereign Consulting to construct the PFAS Treatment Facility located in Midland Park. This is part of Ridgewood Water's commitment to investing into the future sustainability of the Ridgewood Water water system and executing the PFAS Treatment Master Plan. This treatment facility will be treating 9 wells in the system.

For more information on individual facilities, please see below. 

 

 

 

Take a Look at our PFAS Treatment Facilities

Carr Treatment Facility 

Project Status: Construction Completed; Facility in Operation

Completed: September 2019

Twinney Treatment Facility

Project Status: Construction Completed; Facility in Operation

Completed:  August 2022

Ravine Treatment Facility

Project Status: Under Construction; Began in April 2023

Expected Date of Completion: November 2025

Prospect Treatment Facility 

Project Status: Under Construction; Began in August 2023

Expected Date of Completion: October 2025

East Ridgewood Treatment Facility

Project Status: Under Construction; Began in August 2024.

Expected Date of Completion: January 2026

West End Treatment Facility

Project Status: Under Construction; Began in August 2024

Expected Date of Completion: January 2026

Ames Treatment Facility

Project Status: Under Construction; Began in April 2024

Expected Date of Completion: April 2026

Wortendyke Treatment Facility

Project Status: Under Construction; Began in October 2024

Expected Date of Completion: February 2026

Cedar Hill Treatment Facility

Project Status: Under final design and permitting; Pending cultural resource approval, construction will begin in Fall 2025; Bid Opening Scheduled for October 9th 2025

Expected Date of Completion: December 2026*

Eastside Treatment Facility

Project Status: Anticipated start date September 2025

Expected Date of Completion: October 2026*

 

Main Treatment Facility

Project Status: Under final design and permitting; Construction planned to begin Fall 2025

Expected Date of Completion: October 2026*

Mountain Treatment Facility

Project Status: Anticipated start date of September 2025

Expected Date of Completion: October 2026*

*Pending Award Date